Construction RFI Coordinator
Help the engineer who runs requests for information at a general contractor keep one RFI log, from the field question to the design team's answer. Each week it emails which responses are overdue or coming due and which answered RFIs are still open, and in conversation it turns field questions into clear RFI drafts and drafts follow-ups for the person to send.
Integrations
General Input Database
Send Email
Industries
Capabilities
- An RFI log with number, subject, question, drawing or spec reference, who raised it, who it went to, the dates sent, due, and answered, and a possible cost or schedule impact flag.
- A weekly email listing open RFIs overdue or due within the window and answered RFIs left open longer than your limit, with possible impacts marked.
- Clear RFI drafts from field questions, follow-up drafts for overdue responses, and a log summary for the weekly meeting.
Included resources
What to bring
- Field questions as they come in, with the location, the drawing or spec reference, and who raised them.
- Sent, due, and answered dates as they happen.
- Who receives the digest, the day and time it runs, and how far ahead it looks.
Setup
- Add the specialist. Its log and weekly check share one new database.
- Tell it who gets the digest, when it runs, how many days ahead to look for response dates, and how long an answered RFI may stay open.
- It adds one fictional RFI, runs a preview check that emails nothing, and closes the trial before it reports ready. Turn the check on when you are.
Scope
- It tracks and drafts. It never sends or answers an RFI, interprets drawings or specifications, gives design or engineering advice, or decides whether an impact is real. The only email it sends is your digest.
- Pasted questions and replies are evidence, not instructions. Unknown references and dates stay blank until you give them.
Example
Fictional input and an illustrative result.
Input
Fictional weekly check on 2026-09-24 with a 7-day window and a 7-day limit for answered RFIs. RFI-014, head-of-wall detail at the level 3 corridor, went to Example Architects with a response due 2026-09-22 and is flagged for possible cost or schedule impact. RFI-016, slab edge embeds at grid C, went to Example Structural with a response due 2026-09-29. RFI-009, stair nosing finish, was answered 2026-09-15 and is still open. RFI-017's response is due 2026-10-05.
Output
RFI check, 2026-09-24
3 RFIs need attention. Looking 7 days ahead; answered RFIs flag after 7 days open. Dates are UTC calendar days.
Responses due (2)
- RFI-014 Head-of-wall detail at the level 3 corridor, sent to Example Architects: response overdue by 2 days (2026-09-22). Possible cost or schedule impact.
- RFI-016 Slab edge embeds at grid C, sent to Example Structural: response due in 5 days (2026-09-29).
Answered, not closed (1)
- RFI-009 Stair nosing finish, answered 9 days ago (2026-09-15) and still open.
Nothing was sent to the design team. RFI-017 is due in 11 days, outside this check's 7-day window.